Part 1
You have been assigned as a project manager for a small construction company and have been assigned your first project. The client feels they have a basic grasp on their requirements but also feels that they will know more as the project progresses. Using your knowledge of life cycle models, identify two models that may work based on your knowledge of the project.
The scope of the project is as follows:
1. Requirement 1: 3 bedrooms
2. Requirement 2: 2.5 bathrooms
3. Requirement 3: Pool
4. Requirement 4: 2 patios, one patio should be enclosed
Using your experience documenting scope, outline the problem/opportunity statement you are trying to solve for, 2-3 success criteria, and any assumptions, risks, or obstacles.
Part 2
Create a Work Breakdown Structure (WBS) for the following scope:
1. Requirement 1: 3 bedrooms
2. Requirement 2: 2.5 bathrooms
3. Requirement 3: Pool
4. Requirement 4: 2 patios, one patio should be enclosed
Your WBS should be based upon your chosen Life Cycle Methodology and include any deliverables.
Part 3
1. Build a network diagram
2. Identify the early start, early finish, late start late finish for each activity
3. Identify the critical path
4. Identify the duration of the critical path
5. What is the float of Activity B
6. What is the float of Activity H
Activity Predecessor Duration in Days
A Start 3
B Start 6
c A, B 12
D B 5
E D 4
F C 6
G E,F 8
H E 7
I H 3
Environmental policy presentation | SCI256 People, Science And The Environment | University of Phoenix
Your friend, an 8th-grade earth science teacher at the local middle school, is organizing an Earth Day celebration for his students and their families. He knows you have recently been learning about environmental policies in this environmental science class and has asked you to be one of several guest speakers at the event. He […]